Analysis of the Acceleration of Tower Project Activities using the What/If Method
DOI:
https://doi.org/10.33021/pcej.v2i2.5493Abstract
In the construction of the Pegadaian Tower project, the delays experienced were evidenced by the project implementation not being in accordance with the plans that had been designed before the construction process began. The project planning made by the contractor is planned for the topping off process or final floor casting of the superstructure construction phase to be carried out in September 2022 or in the 18th month of the total 25 months of work on this project. Efforts made to adjust the implementation of the plan were to accelerate this project, where the acceleration was carried out using the What/If method by adding working hours (overtime) and the number of workers at the research object who worked on the Mezzanine floor to the 5th floor at the superstructure stage. Apart from the What/If method as an acceleration solution, initial efforts were made by evaluating the project schedule using the Precedence Diagramming Method (DPM) network planning method with the help of Microsoft Project software. The analysis carried out resulted in good acceleration where the acceleration analysis using the What/If method can speed up the completion of superstructure construction so that it can help achieve the topping off target in September according to what has been planned in the schedule. Meanwhile, adding labor and working time to these three important activities can speed up the duration of the project so that the project avoids contract loss penalties with the owner.
References
I. D. Amalia, E. T. Sudjatmiko, and B. M. A. S. A. Bangkara, “Construction Delays Analysis in the Kampung Akuarium Flats Project, Penjaringan-Jakarta,†PRESUNIVE Civil Engineering Journal, vol. 1, no. 2, pp. 70-75, October 2023.
S. Intan, R. S. Alifen, and L. S. Arijanto, “Analisa dan Evaluasi Sisa Material Konstruksi Sumber Penyebab Kuantitas dan Biaya.†Civil Engineering Dimension, vol. 7, no. 1, pp. 36-45, 2005. (In Indonesian)
M. F. M. Djau, T. T. Arsjad, and R. L. Inkiriwang, “Percepatan Pelaksanaan Proyek dengan Penambahan Tenaga Kerja pada Pembangunan Ruko di Jalan Bukit Moria, Tikala Baru,†Jurnal Sipil Statik vol. 9, no. 4, pp. 709-716, 2021. (In Indonesian)
G. A. P. C. Dharmayanti, I. G. A. A. Putera, and M. Y. Prasetya, “Penerapan Metode Fast Tract pada Proyek Unit Layanan Kanker Terpadu RSUD Bali Mandara,†Jurnal Ilmiah Teknik Sipil-A Scientific Journal of Civil Engineering, vol. 25, no. 1, pp. 83-92, 2021. (In Indonesian)
I. Widaningsih, A. L. Maukar, and A. Shinta, “Antisipasi Keterlambatan Proyek Pembangunan Shelter dengan Menggunakan Metode What-If Analysis,†vol. 2, no. 2, pp. 75-84, 2017. (In Indonesian)
P. S. Putri and S.M. Hastanto, “Pengembangan Metode Percepatan Penjadwalan Pada Keterlambatan Proyek EPC di Fase Pelaksanaan dengan Analisa What If,†Jurnal Forum Mekanika, vol. 8, no. 2, pp. 43-50, 2019. (In Indonesian)
Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK guide), Pennsylvania: Project Management Institute, 2013.
A. D. Irianto, Perbandingan Waktu dan Biaya proyek antara Jam Kerja Lembur dan Penambahan Tenaga Kerja pada Pekerjaan Struktur, (Studi Kasus: Perumahan Mukti Sendangadi Residence), Universitas Islam Indonesia Yogyakarta, 2019. (In Indonesian)
D. A. Sofia and A. A. E. Putri, “Analisis Perbandingan Penambahan Jam Kerja dan Tenaga Kerja terhadap Waktu dan Biaya Proyek dengan Metode Time Cost Trade Off,†Prosiding The 12th Industrial Research Workshop and National Seminar, Bandung, 2021. (In Indonesian)
I. Soeharto, Manajemen Proyek, Jakarta: Erlangga, 1997. (In Indonesian)
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).