Analysis of Factors Causing Delay in the Project of Installing Magnet Separators on the Barge Loading Conveyor (BLC) System
DOI:
https://doi.org/10.33021/pcej.v4i1.6599Keywords:
Project delay, material procurement, manpower, Schedule Performance Index (SPI), critical pathAbstract
Project delays frequently occur in industrial equipment installation projects and significantly affect time performance and contractual commitments. This research aims to identify the dominant factors causing delays in the magnet separator installation project on the Barge Loading Conveyor (BLC) system and to propose practical solutions to improve schedule performance. The research focuses on administrative and material procurement factors as well as manpower factors, in line with the project characteristics. A quantitative–descriptive method was applied using baseline schedule analysis, planned and actual S-curve comparison, weekly and cumulative progress deviation calculations, and Schedule Performance Index (SPI) analysis. The results were supported by interviews with project stakeholders. The findings reveal that delays in administrative processes and procurement approval of the main equipment significantly impacted the project because these activities were on the critical path. In addition, limited manpower competency reduced field productivity, resulting in cumulative schedule deviations with SPI values below 1. The research concludes that procurement and manpower are the most dominant delay factors and emphasizes the importance of preventive planning strategies, including clear project day zero determination, integrated procurement scheduling, competency-based workforce planning, and detailed milestone control.
References
Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2020). Causes of delay in the global construction industry: A meta-analytical review. International Journal of Construction Management, 20(3), 1–13. https://doi.org/10.1080/15623599.2019.1627360
Zhang, X., Li, H., & Wu, Z. (2021). Schedule delay risks in mechanical installation projects of bulk material handling systems. Journal of Construction Engineering and Management, 147(5).
https://doi.org/10.1061/(ASCE)CO.1943-7862.0002047
I. Bali, W. Kushartomo, and Jonathan, “Effect of In-Situ Curing on Compressive Strength of Reactive Powder Concrete,” MATEC Web of Conferences, vol. 67 (03013), pp. 1-6, 2016Banobi, E. T., & Jung, W. (2019). Causes and mitigation strategies of delay in power construction projects: Gaps between owners and contractors. Sustainability, 11(21), 5973. https://doi.org/10.3390/su11215973.
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479–489. https://doi.org/10.1016/j.ijproman.2011.10.004
Azahra, A., & Girsang, H. (2025). Analysis of factors causing delays in the development and construction building project. Jurnal Gradasi Teknik Sipil, 9(1).https://doi.org/10.31961/gradasi.v9i1.14366
Vrijhoef, R., & Koskela, L. (2000). The four roles of supply chain management in construction. European Journal of Purchasing & Supply Management, 6(3–4), 169–178.https://doi.org/10.1016/S0969-7012(00)00013-7.
Kerzner, H. (2009). Project management: A systems approach to planning, scheduling, and controlling (10th ed.). John Wiley & Sons.
Sarwani, I., Baihaqi, I., & Utomo, C. (2024). Causes of delay in EPC projects: The case of Indonesia. International Journal on Advanced Science, Engineering and Information Technology, 14(2),
–628.https://doi.org/10.18517/ijaseit.14.2.19744.
Rosyidin, I. F., & Bayuaji, R. (2024). Analysis of the causes of delays and over budget and mitigation to overcome them in construction projects. Jurnal Indonesia Sosial Teknologi, 5(3),
–1285.https://doi.org/10.59141/jist.v5i3.984
Hasmori, M. F., Said, I., Deraman, R., Abas, N. H., & Nagapan, S. (2018). Significant factors of construction delays among contractors in Klang Valley. International Journal of Integrated Engineering, 10(3), 143–151. https://publisher.uthm.edu.my/ojs/index.php/ijie/article/view/2623
Fikri, M., & Madelan, S. (2024). Evaluasi waktu dan biaya instalasi damper pada proyek combine cycle PLTGU.
Indikator: Jurnal Ilmiah Manajemen dan Bisnis. http://dx.doi.org/10.22441/indikator.v3i3.7429
Mohammed, Z., & Bello, U. (2022). Causes of delay in construction projects: A systematic review. International Journal of Engineering Research & Technology (IJERT), 11(2), 227–235. https://www.ijert.org/causes-of-delay-in-construction-projects-a-systematic-review
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).