A risk management model for minimizing cost overruns in interior fit-out projects: Literature review
DOI:
https://doi.org/10.33021/jaaf.v9i2.6422Keywords:
interior fit-out, cost overruns, risk management, design change, procurement risk, ISO 31000Abstract
Cost overruns remain a persistent problem in interior fit-out projects due to high levels of design customization, compressed delivery schedules, and intensive coordination among multiple trades. Although construction risk management frameworks such as ISO 31000 and the PMBOK Guide provide general guidance, they are largely generic and do not fully address the operational characteristics of interior fit-out delivery, particularly under fast-track conditions. This study aims to develop a conceptual risk management model for minimizing cost overruns in interior fit-out projects through a systematic synthesis of existing literature. The research adopts a qualitative exploratory approach based on a systematic literature review of peer-reviewed journal articles, international standards, and authoritative construction management sources published between 2010 and 2025. A thematic content analysis was conducted to identify recurring risk drivers, cost escalation mechanisms, and mitigation strategies relevant to interior fit-out projects. The study does not involve empirical project testing; instead, it consolidates patterns reported across multiple independent studies to construct a theoretically grounded framework. The findings indicate that cost overruns in interior fit-out projects are primarily driven by five interrelated risk domains: design and scope volatility, procurement and supply-chain constraints, financial and budgeting weaknesses, coordination and management deficiencies, and external contextual factors such as regulatory changes and economic instability. These domains influence multiple cost dimensions, including rework and variation costs, procurement escalation, delay-related overheads, and compliance-related expenditures. Based on this synthesis, the study proposes a fit-out–oriented risk management framework emphasizing early design stabilization, proactive procurement planning, structured cost buffering, agile coordination mechanisms, and adaptive contingency management. The study contributes by integrating fragmented risk management knowledge into a coherent conceptual model tailored to interior fit-out project delivery and provides a foundation for future empirical validation.
References
Abdelalim, A. M., Salem, M., Salem, M., Al-Adwani, M., & Tantawy, M. (2024). An analysis of factors contributing to cost overruns in the global construction industry. Buildings, 15(1), Article 18. https://doi.org/10.3390/buildings15010018
Aljohani, A., Ahiaga-Dagbui, D., & Moore, D. (2017). Construction projects cost overrun: What does the literature tell us? International Journal of Innovation, Management and Technology, 8(2), 137–143. https://doi.org/10.18178/ijimt.2017.8.2.717
Alshihri, S., Al-Gahtani, K., & Almohsen, A. (2022). Risk factors that lead to time and cost overruns of building projects in Saudi Arabia. Buildings, 12(7), Article 902. https://doi.org/10.3390/buildings12070902
Balavenkatesh, S., & Arulselvan, S. (2017). Analysis of cost overrun in fast-track interior fit-out projects. International Research Journal of Engineering and Technology, 4(4), 31–34.
Barafort, B., Mesquida, A.-L., & Mas, A. (2018a). Integrated risk management process assessment model for IT organizations based on ISO 31000 in an ISO multi-standards context. Computer Standards & Interfaces, 60, 57–66. https://doi.org/10.1016/j.csi.2018.04.010
Barafort, B., Mesquida, A.-L., & Mas, A. (2018b). ISO 31000-based integrated risk management process assessment model for IT organizations. Journal of Software: Evolution and Process, 31(1), e1984. https://doi.org/10.1002/smr.1984
Björnsdóttir, S. H., Jensson, P., Boer, R. J., & Thorsteinsson, S. E. (2021). The importance of risk management: What is missing in ISO standards? Risk Analysis, 42(4), 764–779.
Bolton, S., Wedawatta, G., Wanigarathna, N., & Malalgoda, C. (2022). Late payment to subcontractors in the construction industry. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 14(4). https://doi.org/10.1061/(ASCE)LA.1943-4170.0000552
Halder, A. (2024). Risk management practices in interior construction projects: A review of challenges and implications. Journal of Construction Project Management, 6(1), 45–58.
Hutchins, G. (2018). ISO 31000:2018 enterprise risk management. Quality Plus Engineering.
Hwang, B.-G., Zhao, X., & Toh, L. P. (2014). Risk management in small construction projects in Singapore: Status, barriers and impact. International Journal of Project Management, 32(1), 116–124. https://doi.org/10.1016/j.ijproman.2013.01.007
International Organization for Standardization. (2018). ISO 31000:2018 risk management—Guidelines. ISO.
Jarkas, A. M. (2015). Rework in building construction: Principal culprits and underlying causes. International Journal of Forensic Engineering, 2(4), 265–279.
Kendall, S. (2011). Developments toward a residential fit-out industry. Open House International, 36(1), 86–94. https://doi.org/10.1108/OHI-01-2011-B0010
Kochar, D., & Rastogi, A. (2023). Challenges and integration of digitalization in fit-out projects. Zenodo.
Kuinkel, M. S., Zhang, C., Felton, G., Demirkesen, S., & Li, H. (2024). Compromise or problem solve: Conflicts in construction schedule updates. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 16(1).
Kutsch, E., & Hall, M. (2009). The rational choice of not applying project risk management in information technology projects. Project Management Journal, 40(3), 72–81. https://doi.org/10.1002/pmj.20112
Liu, J., Xie, Q., Xia, B., & Bridge, A. J. (2017). Impact of design risk on the performance of design–build projects. Journal of Construction Engineering and Management, 143(6), Article 04017010. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001299
Manthanwar, D. C., & Dungi, J. K. (2023). Risk assessment for fast-tracked commercial interior fit-out IT/ITES projects in India. The Asian Review of Civil Engineering, 12(1), 24–28.
Mello, M. H., Strandhagen, J. O., & Alfnes, E. (2015). The role of coordination in avoiding project delays in an engineer-to-order supply chain. Journal of Manufacturing Technology Management, 26(3), 429–454. https://doi.org/10.1108/JMTM-03-2013-0021
Olechowski, A., Oehmen, J., Seering, W., & Ben-Daya, M. (2016). The professionalization of risk management: What role can the ISO 31000 risk management principles play? International Journal of Project Management, 34(8), 1568–1578. https://doi.org/10.1016/j.ijproman.2016.08.002
Peters, E., Subar, K., & Martin, H. (2019). Late payment and nonpayment within the construction industry: Causes, effects, and solutions. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 11(3). https://doi.org/10.1061/(ASCE)LA.1943-4170.0000314
Pielichaty, H., Els, G., Reed, I., & Mawer, V. (2016). Events project management. Routledge.
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® Guide) (6th ed.). PMI.
Sheamar, S., Wedawatta, G., Tennakoon, M., Palliyaguru, R., & Antwi-Afari, M. F. (2023). The potential of new models of construction procurement to counter cost overruns in construction projects. Journal of Financial Management of Property and Construction, 29(2). https://doi.org/10.1108/JFMPC-08-2022-0035
Silva Rampini, G. H., Takia, H., & Berssaneti, F. T. (2019). Critical success factors of risk management with the advent of ISO 31000:2018. Procedia Manufacturing, 39, 894–903. https://doi.org/10.1016/j.promfg.2020.01.400
Tang, S. L. (2003). Modern construction project management. Hong Kong University Press.
Tolentino, R., Amila, D., Skelton, L., & Guan, Z. (2025). Evaluating the effectiveness of design–build project delivery method in commercial interior design and fit-out projects. In Proceedings of the International Conference on Construction Management. Springer.
Walker, A. (2015). Project management in construction (6th ed.). Wiley-Blackwell.
Yap, J. B. H., Abdul-Rahman, H., Wang, C., & Skitmore, M. (2018). Exploring the underlying factors inducing design changes during building production. Production Planning & Control, 29(7), 586–601. https://doi.org/10.1080/09537287.2018.1448127
Zaneldin, E., & Ahmed, W. (2024). A generic framework for managing schedule and cost risks of construction activities using PERT and the EV technique. Buildings, 14(7), Article 1918. https://doi.org/10.3390/buildings14071918